Elena Rossi is Head of Purchasing at Bergwerk Präzision AG. Ask Elena about: suppliers, steel and other material, contracts.
Open actions
- Add the certificate-with-every-delivery rule to the Stahl Nord framework contract as an annex (due 31.10.2026) · Supplier switch to Stahl Nord · from TCK-0457: Stahl Nord trial order delivered without 3.1 certificate
- Tell Acier Léman about the change and agree the backup volume (due 13.11.2026) · Supplier switch to Stahl Nord · from Decision memo: steel supplier from 2027
- Agree the January delivery schedule with Stahl Nord (due 20.11.2026) · Supplier switch to Stahl Nord · from Stahl Nord onboarding call
Decisions
- 09.03.2026 · Replace BW-Classic with NovaERP, hosted in a Swiss data centre
- 14.09.2026 · The Line 3 retrofit window is 02.11.2026 to 13.11.2026; Line 3 restarts on 16.11.2026
- 07.10.2026 · Any delivery that arrives without a 3.1 material certificate goes into quarantine…
- 28.10.2026 · Stahl Nord sends the 3.1 certificate electronically with the delivery note, so goods…
Done actions (3)
- Done: Order eight spare spindle bearings (due 12.06.2026) · Line 3 retrofit · from TCK-0412: Line 3 spindle 2 vibration and surface marks
- Done: Get a binding offer and a trial delivery from Stahl Nord (due 31.07.2026) · Supplier switch to Stahl Nord · from Supplier review: steel bar stock
- Done: Sign the framework contract with Stahl Nord (due 15.10.2026) · Supplier switch to Stahl Nord · from Decision memo: steel supplier from 2027
Projects
Mentioned in
- 12.01.2026 · Staff directory: Bergwerk Präzision AG
- 09.03.2026 · ERP migration kick-off
- 18.05.2026 · TCK-0412: Line 3 spindle 2 vibration and surface marks
- 15.06.2026 · Supplier review: steel bar stock
- 27.08.2026 · Decision memo: steel supplier from 2027
- 14.09.2026 · Weekly production meeting
- 07.10.2026 · TCK-0457: Stahl Nord trial order delivered without 3.1 certificate
- 12.10.2026 · Onboarding note: your first week in production
- 28.10.2026 · Stahl Nord onboarding call