Owner: Reto Ammann, Head of IT. Tag: #erp-migration.
Open actions
- Reto Ammann: Delete or archive the unused variant BOMs (due 20.11.2026) · from TCK-0433: ERP test migration fails on variant BOMs
- Reto Ammann: Run the third test migration (due 27.11.2026) · from TCK-0433: ERP test migration fails on variant BOMs
- Sandra Meier: Plan the 2026 year-end closing in BW-Classic (due 30.11.2026) · from Decision memo: new ERP go-live date
- Reto Ammann: Create Stahl Nord as a supplier in NovaERP (due 11.12.2026) · from Decision memo: steel supplier from 2027
- Reto Ammann: Set up electronic delivery notes from Stahl Nord in NovaERP (due 11.12.2026) · from Stahl Nord onboarding call
- Reto Ammann: Train the key users in NovaERP (due 18.12.2026) · from Decision memo: new ERP go-live date
Decisions
- 09.03.2026 · Replace BW-Classic with NovaERP, hosted in a Swiss data centre
- 09.03.2026 · Reto Ammann owns the ERP migration; Sandra Meier is the sponsor and signs off the budget…
- 06.07.2026 · Clean up the legacy variant BOMs in BW-Classic before the migration instead of migrating…
- 29.09.2026 · Move the ERP go-live from 01.12.2026 to 11.01.2027
- 29.09.2026 · BW-Classic stays available read-only until 31.12.2027 for look-ups
Done actions (6)
- Done: Lukas Brunner: Name two key users from production (due 20.03.2026) · from ERP migration kick-off
- Done: Sandra Meier: Book the budget in the 2026 investment plan (due 31.03.2026) · from ERP migration kick-off
- Done: Reto Ammann: Draft the migration plan with NovaERP (due 10.04.2026) · from ERP migration kick-off
- Done: Lukas Brunner: Mark which variant BOMs production still uses (due 28.08.2026) · from TCK-0433: ERP test migration fails on variant BOMs
- Done: Reto Ammann: Agree the new go-live date with NovaERP (due 09.10.2026) · from Decision memo: new ERP go-live date
- Done: Martina Keller: Tell all staff about the new go-live date (due 16.10.2026) · from Decision memo: new ERP go-live date
People
- Reto Ammann, owner
- Martina Keller, CEO
- Sandra Meier, CFO
- Lukas Brunner, Head of Production
- Elena Rossi, Head of Purchasing
Sources
- 12.01.2026 · Staff directory: Bergwerk Präzision AG
- 09.03.2026 · ERP migration kick-off
- 06.07.2026 · TCK-0433: ERP test migration fails on variant BOMs
- 27.08.2026 · Decision memo: steel supplier from 2027
- 29.09.2026 · Decision memo: new ERP go-live date
- 12.10.2026 · Onboarding note: your first week in production
- 28.10.2026 · Stahl Nord onboarding call