[1] The Line 3 retrofit window is 02.11.2026 to 13.11.2026; Line 3 restarts on 16.11.2026
Decided on 14.09.2026 in Weekly production meeting.
Open note -
[2] Weekly production meeting · Line 3 retrofit #line-3-retrofit
Aarmatic confirmed delivery of the new controls for week 44. The retrofit needs Line 3 to stop for two weeks; Lukas Brunner moved the titanium orders for Novamed to Line 4 and to October. Decision: The Line 3 retrofit window is 02.11.2026 to 13.11.2026; Line 3 restarts on 16.11.2026.
Open note -
[3] Line 3 retrofit · Open actions
☐ Lukas Brunner: Plan extra shifts on Line 4 for the moved titanium orders (due 23.10.2026) · from Weekly production meeting ☐ Thomas Huber: Define the first-article inspection plan for the restart of Line 3 (due 30.10.2026) · from Line 3 retrofit: planning meeting ☐ Nina Frei: Prepare the spindle bearing swap for the retrofit window (due 30.10.2026) · from Weekly production meeting ☐ Lukas Brunner: Tell Novamed about the lower output in week 47 (due 09.11.2026) · from Line 3 retrofit: check-in before the stop ☐ Lukas Brunner: Shadow Nina Frei during the bearing swap in the retrofit window (due 13.11.2026) · from Knowledge handover: Nina Frei, maintenance ☐ Nina Frei: Hand over the sensor alarm thresholds to Lukas Brunner (due 13.11.2026) · from Line 3 retrofit: check-in before the stop ☐ Thomas Huber: Inspect the first five parts after the restart (due 17.11.2026) · from Line 3 retrofit: check-in before the stop ☐ Nina Frei: Record a short video of the calibration with the reference mandrel (due 20.11.2026) · from Knowledge handover: Nina Frei, maintenance ☐ Lukas Brunner: Make sure Line 3 is clean and running for the plant tour (due 20.11.2026) · from ISO 9001 recertification: audit preparation ☐ Thomas Huber: Add the monthly spindle check to the maintenance plan (due 27.11.2026) · from Knowledge handover: Nina Frei, maintenance
Open note -
[4] Onboarding note: your first week in production · What is happening this autumn
• Line 3 is stopped from 02.11. to 13.11.2026 for the retrofit (#line-3-retrofit). • The ISO 9001 recertification audit is on 24 and 25 November 2026 (#iso-recertification).
Open note -
[5] Line 3 retrofit: check-in before the stop Added by a visitor
• Action: @Nina Frei hand over the sensor alarm thresholds to Lukas Brunner (due 2026-11-13) • Action: @Thomas Huber inspect the first five parts after the restart (due 2026-11-17) • Action: @Lukas Brunner tell Novamed about the lower output in week 47 (due 2026-11-09)