Meeting notes from 28.10.2026, added by a visitor in this demo. Captured 1 decision and 3 actions; mentions 3 people and 1 project.
Decisions
Actions
- Nina Frei: Hand over the sensor alarm thresholds to Lukas Brunner (due 13.11.2026) · Line 3 retrofit
- Thomas Huber: Inspect the first five parts after the restart (due 17.11.2026) · Line 3 retrofit
- Lukas Brunner: Tell Novamed about the lower output in week 47 (due 09.11.2026) · Line 3 retrofit
People mentioned
Projects
Original text
Date: 2026-10-28
Type: Meeting notes
Attendees: Lukas Brunner, Nina Frei, Thomas Huber
Tags: #line-3-retrofit
Aarmatic delivered the new controls. The bearing swap on all four spindles is planned for the first three days of the retrofit window.
Decision: Line 3 runs at 80 % feed rate in the first week after the restart.
Why: the new controls and the new bearings need a running-in period before full speed.
- Action: @Nina Frei hand over the sensor alarm thresholds to Lukas Brunner (due 2026-11-13)
- Action: @Thomas Huber inspect the first five parts after the restart (due 2026-11-17)
- Action: @Lukas Brunner tell Novamed about the lower output in week 47 (due 2026-11-09)