[1] Line 3 retrofit: check-in before the stop Added by a visitor
Aarmatic delivered the new controls. The bearing swap on all four spindles is planned for the first three days of the retrofit window. Decision: Line 3 runs at 80 % feed rate in the first week after the restart. Why: the new controls and the new bearings need a running-in period before full speed.
Open note -
[2] Line 3 retrofit: planning meeting · Retrofit or replace?
Decision: Fit vibration sensors on all four spindles of Line 3, so bearing wear shows up before a breakdown. Why: two of last year's unplanned stops were bearing failures that Nina Frei could hear days before they happened.
Open note -
[3] Line 3 runs at 80 % feed rate in the first week after the restart Added by a visitor
Decided on 28.10.2026 in Line 3 retrofit: check-in before the stop (added by a visitor in this demo). Why: • the new controls and the new bearings need a running-in period before full speed.
Open note -
[4] Line 3 retrofit: check-in before the stop Added by a visitor
• Action: @Nina Frei hand over the sensor alarm thresholds to Lukas Brunner (due 2026-11-13) • Action: @Thomas Huber inspect the first five parts after the restart (due 2026-11-17) • Action: @Lukas Brunner tell Novamed about the lower output in week 47 (due 2026-11-09)
Open note -
[5] Fit vibration sensors on all four spindles of Line 3, so bearing wear shows up before a breakdown
Decided on 20.04.2026 in Line 3 retrofit: planning meeting. Why: • two of last year's unplanned stops were bearing failures that Nina Frei could hear days before they happened.
Open note