[1] TCK-0433: ERP test migration fails on variant BOMs · Problem
The second test migration into NovaERP stopped at the bill of materials (BOM) import. 1'214 of 3'870 BOMs failed. All failed BOMs are variant BOMs that were copied by hand in BW-Classic between 2009 and 2015; many point to parts that no longer exist.
Open note -
[2] TCK-0433: ERP test migration fails on variant BOMs · Workaround
Reto Ammann skipped the failed BOMs to test the rest of the import. Finance and purchasing data imported cleanly. Decision: Clean up the legacy variant BOMs in BW-Classic before the migration instead of migrating them as they are. Why: about a third of the variant BOMs point to parts that no longer exist; migrating them would copy the mess into NovaERP.
Open note -
[3] Decision memo: new ERP go-live date · Situation
The plan was to go live with NovaERP on 01.12.2026. Three things make that risky: • The clean-up of variant BOMs (see TCK-0433) is only half done. • December has the year-end closing and the yearly stock count; finance cannot test the new system at the same time. • The Line 3 retrofit ties up the production key users until mid-November.
Open note -
[4] ERP migration · Open actions
☐ Reto Ammann: Delete or archive the unused variant BOMs (due 20.11.2026) · from TCK-0433: ERP test migration fails on variant BOMs ☐ Reto Ammann: Run the third test migration (due 27.11.2026) · from TCK-0433: ERP test migration fails on variant BOMs ☐ Sandra Meier: Plan the 2026 year-end closing in BW-Classic (due 30.11.2026) · from Decision memo: new ERP go-live date ☐ Reto Ammann: Create Stahl Nord as a supplier in NovaERP (due 11.12.2026) · from Decision memo: steel supplier from 2027 ☐ Reto Ammann: Set up electronic delivery notes from Stahl Nord in NovaERP (due 11.12.2026) · from Stahl Nord onboarding call ☐ Reto Ammann: Train the key users in NovaERP (due 18.12.2026) · from Decision memo: new ERP go-live date
Open note -
[5] ERP migration kick-off · Options discussed
• Upgrade BW-Classic: cheapest in the short term, but the developer risk stays. • NovaERP (cloud, Swiss data centre): standard production module, bills of materials (BOM) with variants, Swiss VAT and payroll. • Two other vendors were too expensive for a company of our size.
Open note