[1] Weekly production meeting · Line 3 retrofit #line-3-retrofit
Aarmatic confirmed delivery of the new controls for week 44. The retrofit needs Line 3 to stop for two weeks; Lukas Brunner moved the titanium orders for Novamed to Line 4 and to October. Decision: The Line 3 retrofit window is 02.11.2026 to 13.11.2026; Line 3 restarts on 16.11.2026.
Open note -
[2] Weekly production meeting · Line 3 retrofit #line-3-retrofit
• Action: @Lukas Brunner confirm the retrofit window with Aarmatic in writing (due 2026-09-25) (done) • Action: @Nina Frei prepare the spindle bearing swap for the retrofit window (due 2026-10-30) • Action: @Lukas Brunner plan extra shifts on Line 4 for the moved titanium orders (due 2026-10-23)
Open note -
[4] Line 3 retrofit: planning meeting · Retrofit or replace?
Lukas compared two offers. A new machining centre costs about CHF 1.1 million and takes 9 months to deliver. A retrofit by Aarmatic (new controls, spindle sensors, coolant filter) costs CHF 380'000 and needs two weeks of downtime. Decision: Retrofit Line 3 instead of buying a new machining centre. Why: the retrofit costs about a third of a new machine, and Line 3 is back in production after two weeks instead of nine months.
Open note -
[5] Retrofit Line 3 instead of buying a new machining centre
Decided on 20.04.2026 in Line 3 retrofit: planning meeting. Why: • the retrofit costs about a third of a new machine, and Line 3 is back in production after two weeks instead of nine months.