Meeting notes from 19.10.2026. Captured 2 decisions and 3 actions; mentions 3 people and 1 project.
Decisions
- Lukas Brunner takes over maintenance planning for all lines from 01.12.2026
- Spindle checks on Line 3 happen every month and after every crash, using Nina's five…
Actions
- Nina Frei: Record a short video of the calibration with the reference mandrel (due 20.11.2026) · Line 3 retrofit
- Lukas Brunner: Shadow Nina Frei during the bearing swap in the retrofit window (due 13.11.2026) · Line 3 retrofit
- Thomas Huber: Add the monthly spindle check to the maintenance plan (due 27.11.2026) · Line 3 retrofit
People mentioned
Projects
Original text
Date: 2026-10-19
Type: Meeting notes
Attendees: Nina Frei, Lukas Brunner, Thomas Huber
Tags: #line-3-retrofit
Nina Frei leaves Bergwerk Präzision AG on 30.11.2026 after 17 years. This session captured what she knows that is not written down anywhere else.
How to calibrate the Line 3 spindles
- Warm the spindle up for 15 minutes at 6'000 rpm. Cold readings always look too good.
- Clamp the reference mandrel from the blue case, not the grey one; the grey one is bent.
- Measure the runout at the tip with the dial gauge. Target: 2 µm or less. Above 4 µm, check the tool holder before you blame the bearing.
- Measure vibration at 6'000, 9'000 and 12'000 rpm. Above 2.8 mm/s at any speed, plan a bearing check within a week.
- Write all readings into the maintenance log, with the spindle hours.
Things only Nina knew
- Spindle 4 always reads 0.3 mm/s higher than the others; that is the mounting, not wear.
- The Aarmatic service hotline is slow; call their technician Marco Bianchi directly. His number is on page 2 of the maintenance binder.
- The coolant filter on Line 3 clogs every 6 weeks in summer. The new filter from the retrofit should fix this.
Decision: Lukas Brunner takes over maintenance planning for all lines from 01.12.2026.
Decision: Spindle checks on Line 3 happen every month and after every crash, using Nina's five steps: warm-up, reference mandrel, runout, vibration, log.
- Action: @Nina Frei record a short video of the calibration with the reference mandrel (due 2026-11-20)
- Action: @Lukas Brunner shadow Nina Frei during the bearing swap in the retrofit window (due 2026-11-13)
- Action: @Thomas Huber add the monthly spindle check to the maintenance plan (due 2026-11-27)