Ask
Answers come from the notes, with the source of every passage.
Answer
No AI model in this demo: these are the best-matching passages from the notes. On a real install, a model writes the answer from these citations.-
[1] Supplier switch to Stahl Nord
Owner: Elena Rossi, Head of Purchasing. Tag: #stahl-nord-switch.
Open note -
[2] Switch our main steel supplier from Acier Léman to Stahl Nord from 01.01.2027
Decided on 27.08.2026 in Decision memo: steel supplier from 2027. Why: • Stahl Nord is about CHF 76'000 a year cheaper once the cost of late deliveries is counted. • Stahl Nord delivers in 5 days and sends the 3.1 material certificate with every delivery; Acier Léman was late on 9 of 22 deliveries and twice delivered without certificates.
Open note -
[3] Weekly production meeting · Stahl Nord #stahl-nord-switch
Elena Rossi: the contract is with the lawyer, signature expected in October. The first regular delivery is planned for 05.01.2027.
Open note -
[4] Supplier switch to Stahl Nord · Open actions
☐ Elena Rossi: Add the certificate-with-every-delivery rule to the Stahl Nord framework contract as an annex (due 31.10.2026) · from TCK-0457: Stahl Nord trial order delivered without 3.1 certificate ☐ Thomas Huber: Add the quarantine step to the goods-receipt work instruction (due 06.11.2026) · from TCK-0457: Stahl Nord trial order delivered without 3.1 certificate ☐ Elena Rossi: Tell Acier Léman about the change and agree the backup volume (due 13.11.2026) · from Decision memo: steel supplier from 2027 ☐ Elena Rossi: Agree the January delivery schedule with Stahl Nord (due 20.11.2026) · from Stahl Nord onboarding call ☐ Reto Ammann: Create Stahl Nord as a supplier in NovaERP (due 11.12.2026) · from Decision memo: steel supplier from 2027 ☐ Reto Ammann: Set up electronic delivery notes from Stahl Nord in NovaERP (due 11.12.2026) · from Stahl Nord onboarding call
Open note -
[5] Decision memo: steel supplier from 2027 · Actions
• Action: @Elena Rossi sign the framework contract with Stahl Nord (due 2026-10-15) (done) • Action: @Elena Rossi tell Acier Léman about the change and agree the backup volume (due 2026-11-13) • Action: @Reto Ammann create Stahl Nord as a supplier in NovaERP (due 2026-12-11)
Open note