  1. [1] Move the ERP go-live from 01.12.2026 to 11.01.2027
    Decided on 29.09.2026 in Decision memo: new ERP go-live date. Why: • finance closes 2026 in BW-Classic and opens 2027 in NovaERP, so we never run two systems inside one financial year. • the BOM clean-up and the third test migration need until the end of November.
    Open note
  2. [2] Decision memo: new ERP go-live date · Actions
    • Action: @Reto Ammann agree the new go-live date with NovaERP (due 2026-10-09) (done) • Action: @Sandra Meier plan the 2026 year-end closing in BW-Classic (due 2026-11-30) • Action: @Reto Ammann train the key users in NovaERP (due 2026-12-18) • Action: @Martina Keller tell all staff about the new go-live date (due 2026-10-16) (done)
    Open note
  3. [3] Decision memo: new ERP go-live date · Situation
    The plan was to go live with NovaERP on 01.12.2026. Three things make that risky: • The clean-up of variant BOMs (see TCK-0433) is only half done. • December has the year-end closing and the yearly stock count; finance cannot test the new system at the same time. • The Line 3 retrofit ties up the production key users until mid-November.
    Open note
  4. [4] BW-Classic stays available read-only until 31.12.2027 for look-ups
    Decided on 29.09.2026 in Decision memo: new ERP go-live date.
    Open note