Ask
Answers come from the notes, with the source of every passage.
Answer
No AI model in this demo: these are the best-matching passages from the notes. On a real install, a model writes the answer from these citations.-
[1] Keep Acier Léman as a backup supplier for stainless 1.4404 only, with a small yearly volume
Decided on 27.08.2026 in Decision memo: steel supplier from 2027. Why: • we do not want to depend on a single steel supplier for medical-grade stainless.
Open note -
[2] Supplier review: steel bar stock · Alternatives
Elena Rossi asked three suppliers for offers: • Stahl Nord AG (Schaffhausen): 5-day lead time, a 3.1 certificate with every delivery, price about 6 % below Acier Léman's current price. • Ferro Ticino SA: good prices, but no stainless 1.4404 in the diameters we need. • A German distributor: 3 weeks lead time, no stock in Switzerland. Sandra Meier wants the full yearly cost, not only the price per kilo: freight and the cost of late deliveries count too.
Open note -
[3] Supplier review: steel bar stock · Where we stand with Acier Léman
Acier Léman SA has supplied our steel bar stock since 2014. In the first half of 2026: • 9 of 22 deliveries were late, on average by 6 working days. • Two deliveries came without the 3.1 material certificate; Thomas Huber had to block the material until the papers arrived. • They announced a price increase of 14 % from January 2027. Lukas Brunner: the late deliveries caused two weekend shifts on Line 2 in May.
Open note